Showing posts with label frame. Show all posts
Showing posts with label frame. Show all posts

Tuesday, December 2, 2008

Rear completed



Dropped in today and met the brickie- a nice young guy. Pleased to see that there is great progress and the back is completed, they are up to the front rooms and hope to finish by early next week. 

The pool paving people called and hope to concrete the beam this Friday and install coping tiles early next week.

This picture is a good candidate for some photo manipulation to see how the finished yard might look with various landscaping options.
rear4black

Another panorama of the rear
rear5


A small problem with damage to the frame meaning they can't work on the front bedroom, nothing to worry about as the frame people will be back to fix in a day or so.
steel frame damage

Sliced bricks ready for windows
sliced bricks

Rainwater plumbing to en suite
P1050822


Main bedroom wall still to be completed
main bedroom wall

Laundry door and study wall looking towards front of the house
P1050814

Wednesday, November 26, 2008

First wall almost complete


Today we found that great progress had been made and almost the entire side wall completed. Looks like the bricks have even been matched and not just put down at random. Hopefully this rate of work will continue and it will be done quickly.

P1050649
external wall
P1050650
Interior detail of brickwork
P1050654

P1050640

P1050638

P1050637

Tuesday, November 25, 2008

Garage wall complete




Second day of bricking and we think it looks great. Spoke to SS today and he thinks that bricks will be done in about three weeks. Even better they won't be painting the gutters and fascias 'till the very end so we have lots of time to decide on colours. Should be easy to photoshop the gutters in various colours after the bricks are up.

P1050613




P1050614

Meterbox
Meter box


That pool is looking good!
P1050622

Monday, November 24, 2008

Bricking has started


Today we got a nice surprise, dropping in for a quick look we found that the brickies have been and started. Even better the mortar choice looks very nice. Hopefully they can get it done well before Christmas to leave time for the post lockup work.




P1050604 This shows how they have moved all of the bricks into nice piles.


P1050606 Another use for our garage, looks like they have even got a chair!

Friday, November 21, 2008

Roof covering fixed


P1050594
Originally uploaded by sdabel
Dropped in this morning around 11.30 to find the roof had just been finished. Colour (Shoal Grey) looks much better on than on the ground so happy with that. Not sure about the colour selections of the gutters and fascias now so might see about changing them, only paint so should not be difficult.

P1050585

Window to laundry has also been replaced with the correct awning style window. Next stage should be the bricks!Laundry Window

Thursday, November 20, 2008

Windows and external door frames fixed

Today the windows and door frames went in.Bedroom Windows

Kitchen window
Kitchen window is composed of glass bricks and will be at bench height. Should provide light without loss of privacy.

P1050575

Tuesday, November 18, 2008

Plumbing hot and cold fixed

,frToday the plumbing was installed, hot, cold and rainwater and connected to mains so we have a working tap.

We specified a tap for the fridge, interesting that this one tap cost almost twice as much as doubling the entire rainwater piping!
Detail of how the pipes pass through the frame.
Plumbing detail

Plumbing for mixer and shower head in En suite shower.


Rainwater fittings.Pump for rainwater will connect to house lines here. Rainwater will be pumped to toilets and laundry, if rainwater tank is empty or power fails the system will cut over to mains water. 

Colorbond roofing delivered

Today the roofing arrived, looks a bit more grey (Shoal Grey) than I had imagined but there it is! Light colour is to reflect as much heat as possible. Zincalume (galv) is the most reflective but many councils including ours will not approve it.

Saturday, November 15, 2008

Gutters installed


Yesterday (friday 14th) the gutters and facias went up. Makes a real difference to how complete the house looks.



P1050467





P1050469
P1050470

P1050471


P1050473


P1050487


P1050485

Wednesday, October 29, 2008

Gas pipe fitted

This picture actually taken on October 28, shows more progress. Mostly in roof structure. Gas pipe has been fitted.

Thursday, October 16, 2008

Frames after day 1


Frames after day 1
Originally uploaded by sdabel
Today we had a look and found that the frames had been started. We now have half a house!

Wednesday, October 15, 2008

Steel Frames delivered


Steel Frames
Originally uploaded by sdabel
Today the steel frames arrived. What you can see in this picture is it, all that is required to build a house. Hopefully the frame will go up very soon now.